The La Mesa Dam is located in Novaliches, Quezon City,
Metro Manila (MM) across the Tullahan River as shown in Figure 3.1.It is one of the two major dams whose
primary purpose is water supply for the entire Metro Manila area.Construction of the dam began in 1926 and
was completed on June 1929; but with the increasing demand, the Metropolitan
Waterworks and Sewerage System (MWSS) decided in 1957 to increase the capacity
of the reservoir by raising the dam.The project was completed in 1958. In 1991, the dam was again raised to a new elevation of 80.15
meters to serve as a buffer zone for flood control.The La Mesa Dam has a watershed area of 27 km2, a
height of 33 meters and a crest length of 326 meters.It has a dependable water supply capacity of 110 million liter
per day (MLD), augmented by water from the Angat Multi-purpose Dam.
Main
Features of La Mesa Dam
Location
:
Brgy. Novaliches,
Quezon City, MM
Coordinates
:
14°40’15” N
121°03’ E
Name of River
:
Tullahan River
Owner
:
MWSS
Purpose
:
Water Supply
Period of
Construction
:
1926 – June 1929
Date of Operation
:
June 1929
Dam
Type
:
Storage, Earth
fill
Drainage Area at Dam site
:
27 square
kilometers
Foundation
:
Solid Rock
Crest Elevation (Parapet)
:
El. 82 m.a.s.l.
Height
:
33 meters
Crest Width
:
6.0 meters
Crest Length
:
326 meters
Base width at maximum section
:
180 meters
Embankment
Impervious Fill
:
630,000 cubic
meters
Filters
:
99,000 cubic
meters
Reservoir
Gross Storage Capacity
:
51.03 million
cubic meters
Dependable Supply
:
110 million liters
per day
Maximum Reservoir level
:
El. 80.15 m.a.s.l.
Minimum Reservoir level
:
El. 71.00 m.a.s.l.
Spillway
Length
:
236.50 meters
Type
:
Concrete Overflow
Structure
Sill Elevation
:
El. 80.15 m.a.s.l.
Penstocks
Type
:
Plate Steel
embodied in concrete
Dimension
:
3 – 2.45 meters
dia. for the horizontal part then reduces to 2.30 meters dia. for the vertical
part
Project Cost
(original project)
:
P 1,875,000
(at 1929 price level)
1st dam raising
:
P950,300 (at 1929 price level)
2nd dam raising
:
P 3,110,300
(at 1929 price level)
Source of Fund
:
Corporate Funds of
MWSS
Construction By
:
Dimson
Construction Co. – For raising of the dam and spillway (1958)
Galauran &
Pilares Const. Co. – For raising of the dikes (1958);
Pacifico Austria
Co. – For raising of the dike and spillway to El. 80.15 m. (1991)